Two Pilots in Material Tracking on the Construction Site
Frederic Meyer, who managed the
RFID portion of the InHaus 2 project, says the goal of using RFID on the construction site for material flow management is to speed the flow of materials and make sure work days are not lost due to the proper materials not being on hand. In addition, Fraunhofer and Hochtief believe RFID can help manage the official safety documentation required by the state after certain building steps are finished, because RFID allows building components to be tracked after construction is complete.
In the first RFID project, which took place in spring 2008, researchers tagged 50 metal casings—frames used as molds when concrete is poured—with
EPC Gen 2 tags to test the feasibility of employing RFID to track the flow of construction materials. The team chose to track casings because, although they knew the metal might interfere with RF signals, the frames are often in high demand, and occasionally the right types are unavailable for workers when needed.
|
|
A truck carrying tagged facade elements passes an RFID gate.
|
The 10-centimeter (4-inch) thick casings are rented from a subcontractor and delivered via truck, stacked 10 high. During the project, when a driver moved his vehicle through a
portal erected at the construction site's entrance, a
Feig Electronic RFID
interrogator was used to
read the casing tags. Researchers found that too much
attenuation of the RF signal affected read rates; what's more, some tags could not be read because the designed
read range was insufficient. During the month-long test, read rates averaged around 30 percent.
A second project at the construction site involved the tracking of facade elements with RFID. When facade elements are delivered, important information about them is manually written on a single paper label attached to each element. The labels, however, are often lost after the first time the facade is cleaned. Researchers tested the viability of replacing the label with an
RFID tag containing a unique ID linked to the information in a database. For the test, the team placed EPC Gen 2 tags on facade elements, and on the crates in which they were transported, in order to track them during the transportation
phase. They also applied a passive
low-frequency (133 kHz) tag on the facade element's frame, for tracking the elements following installation.
|
|
Tagged crates loaded with tagged facade elements.
|
When a truck loaded with crates of facade elements passed through the RFID portal erected at the construction site's entrance, the portal
reader interrogated the
UHF tags. Once the facade elements were installed onto the building, workers could use a handheld RFID interrogator to identify each 133 kHz tag. The facade-tagging project lasted five months, Meyer says, during which time workers were able to read all tags with the handheld reader, as well as at the gate. In this case as well, facility managers can interrogate the tags on the installed facade elements to track their maintenance history.
The InHaus 2 project pulls together the work of nine separate Fraunhofer institutes. For instance, the
Institute for Material Flow and Logistics, in Dortmund, supported the project with logistics. Some 50 industrial partners, as well as universities, are also taking part. With construction now complete, the three-story InHaus 2 building will be used for offices and labs for the Fraunhofer Institute, and rooms can be equipped for testing technologies relevant to the health and senior care sectors, as well as the hotel industry.
Hochtief says it hopes to utilize some of the technologies tested during the construction phase at other sites. In addition, the firm will be responsible for facility management, and be involved in further testing of equipment in the building until the end of 2010.
Hochtief invested €4.3 million ($5.6 million) into the project, and Fraunhofer spent €3.6 million ($4.7 million). Partly funded by the state of North Rhine Westphalia and the
European Union, the partners spent a total of €26.2 million ($34.1 million) on the project.